- Project management activities do not end immediately after the product is completed
- The main purpose of closure is to formally end a project
Types of closure
- Closure activities can be categorized to 2 main types as below
- Administrative closure
- Product is formally accepted by customer
- All stakeholders have no more issues pertaining to the project
- Contract closure
- Relates to ending the work with the vendor
Administrative closure
- Closure activities relating to customer and internal parties (sponsor/team member)
- Activities includes
- Meet with customers /sponsor to gain final approval of the deliverable
- Hand over to support team and begin support/maintenance
- Perform a project review and lesson learnt
- Compile a project report
- Return project resources
- Collect project files and store them for future access
Customer acceptance meeting
- Verify the acceptance criteria for the project have been met
- Obtain customer sign-off
- Dealing with a dissatisfied customer requires an agreement, in writing, on next steps such as:
- Project acceptance with deviations and omissions noted and explained
- Continuation of project until all acceptance/success criteria are achieved
Turning over to support team
- After customer sign-off, turn over the deliverable to the client, the project team will handover the project to support and maintenance team
- The support team will handle the day to day operations (long-term) and provide help to customer if there is any problem
Project review and lesson learnt
- During the process of implementing the project, there are bound to be mistakes made and new and better ways of doing things
- Conduct the review near the end of the project
- Include all team members
Suggested considerations
- 3 approaches to do review and lesson learnt:
- Which aspects were successful?
- What mistakes were made?
- What improvement to be done?
- Areas to consider
- Project definition, scope and team
- Planning
- Cost
- Resources
- Communications
Reflective questions
- What did you enjoy most and why?
- What did you find frustrating and why?
- What was successful?
- What didn’t work?
- What wasn’t achieved
- What would you have done differently?
Benefit of reviews and lessons learned
- So that the next project that is rolled out will not make the same mistake
- Effective methods can be re-used in the next project implemented
Releasing the project team
- Release team members at the end of the project
- Notify functional managers who are the bosses of the team members
Compile a project report
- A final report is:
- History of project
- Synopsis of what went right and wrong
- Account of the life and times of the project
- Account of who worked on the project and in what capacity
- Project report includes:
- A brief description of project
- A measure of success
- Lessons learned
- Explanations for any variances in time or budget
- Recommendations for future projects
Contract closure
- Contract closure is the second type of closure
- The last stage of procurement management which relates to activities involving vendors
- Deals with the vendor when the work is completed
- Project manager has to ensure the following:
- Contract conditions have been met
- Work specified has been completed
- Deliverables have been tested and accepted
- The vendor has been notified that the deliverables have been accepted
Source: PMP, Prince2
No comments:
Post a Comment