Thursday, January 20, 2011

Closing

Closure
  • Project management activities do not end immediately after the product is completed
  • The main purpose of closure is to formally end a project

Types of closure
  • Closure activities can be categorized to 2 main types as below
  • Administrative closure
    • Product is formally accepted by customer
    • All stakeholders have no more issues pertaining to the project
  • Contract closure
    • Relates to ending the work with the vendor

Administrative closure
  • Closure activities relating to customer and internal parties (sponsor/team member)
  • Activities includes
    • Meet with customers /sponsor to gain final approval of the deliverable
    • Hand over to support team and begin support/maintenance
    • Perform a project review and lesson learnt
    • Compile a project report
    • Return project resources
    • Collect project files and store them for future access

Customer acceptance meeting
  • Verify the acceptance criteria for the project have been met
  • Obtain customer sign-off
  • Dealing with a dissatisfied customer requires an agreement, in writing, on next steps such as:
    • Project acceptance with deviations and omissions noted and explained
    • Continuation of project until all acceptance/success criteria are achieved

Turning over to support team
  • After customer sign-off, turn over the deliverable to the client, the project team will handover the project to support and maintenance team
  • The support team will handle the day to day operations (long-term) and provide help to customer if there is any problem

Project review and lesson learnt
  • During the process of implementing the project, there are bound to be mistakes made and new and better ways of doing things
  • Conduct the review near the end of the project
  • Include all team members

Suggested considerations
  • 3 approaches to do review and lesson learnt:
    • Which aspects were successful?
    • What mistakes were made?
    • What improvement to be done?
  • Areas to consider
    • Project definition, scope and team
    • Planning
    • Cost
    • Resources
    • Communications

Reflective questions
  • What did you enjoy most and why?
  • What did you find frustrating and why?
  • What was successful?
  • What didn’t work?
  • What wasn’t achieved
  • What would you have done differently?

Benefit of reviews and lessons learned
  • So that the next project that is rolled out will not make the same mistake
  • Effective methods can be re-used in the next project implemented

Releasing the project team
  • Release team members at the end of the project
  • Notify functional managers who are the bosses of the team members

Compile a project report
  • A final report is:
    • History of project
    • Synopsis of what went right and wrong
    • Account of the life and times of the project
    • Account of who worked on the project and in what capacity
  • Project report includes:
    • A brief description of project
    • A measure of success
    • Lessons learned
    • Explanations for any variances in time or budget
    • Recommendations for future projects

Contract closure
  • Contract closure is the second type of closure
  • The last stage of procurement management which relates to activities involving vendors
  • Deals with the vendor when the work is completed
  • Project manager has to ensure the following:
    • Contract conditions have been met
    • Work specified has been completed
    • Deliverables have been tested and accepted
    • The vendor has been notified that the deliverables have been accepted

Source: PMP, Prince2

No comments:

Post a Comment